Installation Sheet

FV250 Rev. A 7/25/18 Page 4
1. Install stop valve assembly using proper size supply
escutcheon and sweat solder adapter kit if applicable (see
1). Thread sealing compounds should be used on male NPT
threads only.
Aqua ush
®
Installation Instructions
3. Insert the ush valve tailpiece into the stop valve and hand
tighten the lock nut to the stop valve. Plumb the entire unit
(see 3).
4. Determine the length of vacuum breaker tube required to join
the ush valve and xture spud. Cut the vacuum breaker tube,
if re quired, to this length (see 4a). Assemble the vacuum
breaker tube assembly and spud nut assembly to the ush
valve and xture spud (see 4b).
5. Hand tighten spud nut and vacuum breaker tube nut to xture and ush valve. Adjust the valve assembly for plumb. Tighten
xture spud nut, vacuum breaker tube nut and lock nut with a wrench.
2. Prior to inserting the ush valve tailpiece into stop valve, be
certain that the O-ring seal is located in O-ring seal groove at
the end of the tailpiece and the locking nut and locking snap
ring are located as shown below (see 2). Care should be
taken not to damage the O-ring when inserting the tailpiece
into the stop valve. If lubrication is needed, wetting the O-ring
with water will be suf cient.