Installation Checklist
This section provides an installation checklist to assist you with preparing the installation site and installing
the 14-Slot Shelf.
Table 1-1 Installation Checklist
Installation Procedure (See chapters 1 through 5) In-process Completed
SITE PREPARATION VERIFIED
WARNING: Observe all electrical safety precautions when
configuring the external power supplies. This is a high voltage
hazard.
External power supplies configuration verified
Site environmental requirements verified
Protective earth ground verified
UNPACKING THE SHELF
Shipping container inspected for damage
All packing material removed from Shelf
Shipping inventory completed
Front and rear cable trays attached to Shelf
RACK MOUNTING THE SHELF
Rack mounting flange configured
Seismic rack mounting procedures completed
POWER CONNECTION
WARNING: Ensure that all power domain circuit breakers are
switched OFF before connecting power and return cables to the
Shelf. This is a high voltage hazard.
Power and return leads connected to PEMs
External power supply voltages verified
Protective earth ground connected to Shelf