Quick Guide

802699 - G4 - Quick Start Guide - 09.2016 - v2.02
STEP 4- Install the undersink unit
Celsius Unit
Note:
Remove the cap, from the vent, on top of the undersink unit and Install the mains water
braided hoses to the undersink unit before locating the unit in place.
POWER
CORD
USB
MAINS IN
CO2
IN
SPARKLING
OUTLET
BLUE
WHITE
BRAIDED
BRAIDED
Note:
Note:
Trim
Trim
all silicon tubes
all silicon tubes
to minimise
to minimise
any dead leg of
any dead leg of
water
water
Note:
Note:
All
All
silicon tubes
silicon tubes
must be cut to
must be cut to
size. They must
size. They must
have a constant
have a constant
fall back to the
fall back to the
unit.
unit.
RED
CLEAR
BRAIDED
POWER
CORD
MAINS
IN
MIXER
OUT
MIXER
IN
BOILING
OUT
BYPASS
IN
VENT BYPASS
OUT
USB
POWER
CORD
USB
CHILLED
OUTLET
MAINS
IN
BRAIDED
Note:
Note:
Trim
Trim
all silicon tubes
all silicon tubes
to minimise
to minimise
any dead leg of
any dead leg of
water
water
BLUE
Celsius Unit
Model BHA
Model CHA
Model CSHA
Note:
- Mains hose length is 750mm
- Plug and Cord length is 1800mm
Position the under sink unit close to the celsius tap, according to the hose and cord lengths
supplied
Commissioning
OPEN Position
CLOSED Position
ON
OFF
Stop cock
operation
Have a 10L bucket or similar container (not
supplied) at the ready to hold a quantity of
water that will be ejected while the Filter
Flush Mode is in operation. Open the filter
access door on the front of the HydroTap
and the filter cartridge will be exposed.
Located to the rear RHS of the cartridge is a
flush line, approx 600mm long and the flush
line stop cock. Place the valve end of the
flush line into the 10L bucket or container.
1.
Turn the stop cock ON
2.
Press [Start] button to start filter flush.
3.
Allow at least 10 litres of water to flush
through the filter.
4.
Once the filter flush is finished, Turn the stop
cock OFF then press [Stop] to end filter flush
mode.
Flow Calibration:
1.
Press [Next] and the View screen will
show the Flow calibration mode.
2.
Press the [Start] button and the tank will
first empty then fill. Upon completion the
actual pulse will be displayed. Check this
reading is within the limits
Boiling Calibration:
1.
Press [Next] for the Boiling Calibration
screen.
2.
Press the calibration button and the system
will commence the Boiling calibration
procedure. This will take aprox 5-6 minutes.
3.
Upon completion, a Booster reminder screen
will appear and allow you to return home by
pressing the [Home] button.
4.
Check the Date and Time settings (See
section G of the user guide)
To enable the Booster: (when installed)
Press the [MENU] button for main menu.
Press the [Install] button.
Press the [Booster] button.
In the next screen, press YES to enable the
Booster.
Turn the Booster ON
Water must be run through the Booster for
a min of 30 seconds, before the heater will
activate.
Dispense boiling water for 30 seconds and
check the Booster outlet hose is warm when
the boiling water tank is replenishing.
Note
Note: Failing to make the correct selection for the
“Booster”, will affect product performance.
Filter Flush:
Commissioning the HydroTap
Note: Remove the two red caps only if a mixer is fitted.
Note:
Insulate the Blue and White tubes after trimming to length
STEP 5 - Commission the Celsius
Turn on the water and gas to check for any leaks before turning on the power.
The system will promp you to select a language before continuing with the CO
2
Purge and
filter flush procedures
CO
2
Purge: (Model CS175)
Initial Commissioning screen
Language selection screen
1.
Press the [START] button to
commence the purging process.
2.
Purge for 5 seconds and ensure all
water has stopped flowing through
the tap. (You will hear the CO
2
gas
escaping from the tap).
3.
Press the [Stop] button.
4.
Press [Next] for the filter flush
screen
Commissioning
Note:
The tube lengths are matched to the pumps performance and therefore
CANNOT be lengthened