User manual

Control Unit and RTU Installation Procedure
Document Number: ECP 05-9531
Version: 2.0
Date: 03/09/2014
© UK Power Networks 2014 All rights reserved 7 of 29
7 Communications
7.1 Prior to the installation of remote control switchgear it is advisable to carry out a
Paknet communications survey using a Paknet test set (CS1051 or CS106-6) to
determine if a suitable signal strength is available. If this cannot be achieved UK
Power Networks Operational Telecoms (or your UKPN nominated contact) should
be consulted so that an alternative can be established.
7.2 A Paknet aerial can usually be mounted onto the switchgear using the bracket
supplied with the equipment - refer to examples in Figure 7-1 and Figure 7-2. For
equipment that is installed in a GRP it is important to orientate the mounting bracket
on the equipment to ensure the aerial is reasonably upright and not bent over by
the GRP roof. It is often necessary to mount the aerial outside of the GRP to get the
best reception - refer to Figure 7-3.
Figure 7-1 Paknet Aerial Mounting on
Schneider Switchgear
Figure 7-2 Paknet Aerial Mounting on
LUCY Switchgear
Figure 7-3 Paknet Aerial Mounting on a GRP Substation