6.3 - Lamp/Buzzer Test – advanced, service and commissioning users
1.Main Menu>>3.Test Mode>>3.Lamp/Buzzer Test
This option will illuminate all the panels LEDs in sequence, to check they are working properly. The
panel buzzer will also sound. A quick lamp test can be performed from any screen by holding down the
Menu button for 2 seconds.
7.0 - Faults
The panel continuously monitors hardware, battery life and
connections across the system. If a fault is found, it will be
displayed on the panel screen, the buzzer will sound and the
common fault LED will be illuminated. The first line of the display
shows the event number, followed by the zone number and the
type of fault. The second line details the type of device and the
device number. The third line displays any location text (if programmed).
If the panel displays any faults, contact your alarm maintenance or installation company for advice.
8.0 – Maintenance
The Zerio Plus system should be maintained in accordance with the regulations and codes appropriate
to the country of installation. Follow the test schedule recommended by your installer or maintenance
company. This schedule is based on BS5839 codes of practice.
Daily Actions
The user should check that the panel indicates normal operation. If any faults exist, they should be
recorded and the responsible person or maintenance company should be notified.
Weekly Actions
The user should put at least one callpoint or detector in to alarm, checking that the correct device/zone
is indicated on the panel and that the programmed sounders activate. A different device should be
tested this way each week. A lamps test should be carried out and any inactive LEDs reported (refer to
section 8.3).
Quarterly Actions
The maintenance engineer should test at least 25% of detectors and 100% of callpoints. The devices
tested should be varied so that each device will have been tested at some point in any given 12 month
period. The panel battery connections and any relay or input connections should be checked. A visual
inspection of the panel should be carried out. Check that there are no outstanding issues in the
logbook to be addressed. A lamps test should be carried out and any inactive LEDs reported.
Annual Actions
The maintenance engineer should carry out a complete walk test. The panel battery should be tested
(see information below) and replaced if necessary. A dump of the verify table and panel table should
be taken and analysed for any change to previous records. A visual inspection of the panel should be
carried out. A lamps test should be performed and any inactive LEDs reported.
002 Zn:001 REMOVAL
SMOKE DET 001
Kitchen