User Guide
Note 1: These clearances apply except if the listing of an appliance specifi es dif-
ferent clearance, in which case the listed clearance takes precedence.
Note 2: These clearances apply except if a listed wall penetration assembly is 
used.
13. Ensure access to clean out Tee are in accordance with the enforcing authori-
ties and clearances are maintained to your local building codes.
INSTALLATION PROCEDURE
  1. Unroll the Flexible Liner to the maximum allowable length. Take a rope 
slightly longer than the liner and make a knot at one end of the rope and 
place other end through the backside of the Nose Cone and pull the rope until 
the knot is completely in the Nose Cone. Place the Nose Cone at the end of 
liner. To secure, use duct tape or other fastener.
  2. Guide the liner down the chimney (Nose Cone fi rst) using the attached rope, 
to the inlet opening. (see illustration A, on next page.)
  3. Insert the vertical portion of the Base Tee (if used) into the inlet opening 
with the capped end pointing down. Remove the Nose Cone from fl ex liner 
and fasten liner to an “A” Connector using large head stainless steel rivets 
(1/8” size) (use 3 rivets). Fasten the “A” Connector to the top inlet of the 
Base Tee using large head stainless steel rivets (use 3 rivets). To join two 
parts by rivet, drill 3 holes, 9/64”) through the two parts. Then, fasten the 
rivet by using either hydraulic (mechanical) or pneumatic riveter. Use three 
(3) rivets. (see illustration B, on next page.)
  4. Install the horizontal portion of the Base Tee and secure it with two (2) screws 
through the attached brackets. Using a standard mortar mix, cement around 
the horizontal portion of the Base Tee (or mortar guard) at the inlet.
TYPICAL INSTALLATION
MORTAR
GUARD
FLEX ONLY
SINGLE TEE DOUBLE TEE
(preferred method)
– 4 –