SECTION 2 – CHILLER COMMISSIONING
FORM 160.81-NOM2
ISSUE DATE: 2/29/2012
2
PRE-START CHECKLIST
All checkpoints in the following list must be complet-
ed before placing the Rotary Screw Liquid Chiller in
operation. Only when the checklist is completed will
the unit be ready for initial start-up.
Leak Check (Visual)
Thoroughly check all fittings and connections for
oil and refrigerant leaks.
CUSTOMER (OPERATING PERSONNEL)
INSTRUCTION
Operation
Instruct the customer or operating personnel on
the location of all controls and the operation of
the OptiView Control Center.
Maintenance
Review the maintenance schedule with the
customer.
Review the preventative maintenance schedule
with the operating personnel and make certain
that it is thoroughly understood, including the re-
quired oil filter element change after the first 200
hours of operation.
Start-up is an excellent time to log baseline data
from vibration analysis, oil analysis and eddy cur-
rent testing.
CHECKPOINTS
Pressure test before introducing pressure to unit, and check for leaks.
Conrm motor disconnect is open.
Conrm oil level is between the two sight glasses on the oil separator.
Conrm all eld wiring connections have been made.
Conrm Control Center display is operating.
Conrm pressures and temperatures are consistent with anticipated ranges. Conrm heater is operating.
Open discharge service valve.
Conrm the COM, LP, HP ports on the capacity control block valve are back seated.
Conrm all oil return system service valves are open.
Conrm liquid injection service valves are open.
Close motor main disconnect.