Operation Manual
  <4. WIRING>
4-6
IM 01F06A00-01EN
4.5  End Processing Method of DYC Signal Cable
4.5.1  For Vortex Flowmeter (DY-N)
1
2
3
4
5
6
7
8
9
Do not short-circuit the conductive layer and the 
terminals (A, B, C and T
*
1
).
Slide FEP (fluorinated ethylene propylene) tubing 
over the twisted inner and outer drain wires C until 
the tubing cannot be slid any further, and then cut 
off the tubing leaving 5 mm (0.2 in.) of the stranded 
drain wires exposed. 
Slide heat shrinkable tubing over the cable end so 
that the tubing covers the braided shield and 
overlaps both the polyethylene jacket and loose 
wires A, B, C, and T*
1
. 
Slide a short piece of heat shrinkable tubing over 
each of wires A, B, C, and T*
1
. Install a crimp-on 
terminal lug at the tip of each wire. Crimp and 
solder each lug. 
Slide each short piece of heat shrinkable tubing 
over the crimp sleeve. Heat all pieces of heat 
shrinkable tubing with a heat blower or dryer.
Attach an identification label to the end of the cable.
Description Figure
Unit : mm
(approx. inches)
F0407.ai
Strip off the outer polyethylene jacket, outer braided 
shield and inner jacket, and inner braided shield as 
per the dimensions below.
Strip off the black conductive layer convering two 
wires completely, as per the dimensions below.
Twist each of the conductor and drain wires so that 
there are no free strands.
Strip off about 5 mm (0.2 in.) of insulation for each 
of wires A, B, and T*
1
, and twist the strands of each 
wire. Twist the inner and outer drain wires together. 
(*1): Only for /MV
T*
1
 (Yellow)
90 (3.5)
5 (0.2)
10 (0.4)
5 (0.2)
Conductive Layer (Black) 
Conductive Layer (Black) 
A (Red)
T*
1
 (Yellow)
40 (1.6)
5 (0.2)
50 (2.0)
60 (2.4)
B (White)
3 (0.1) 
or less
Drain wires
T*
1
 (Yellow)
5 (0.2)
5 (0.2)
5 (0.2)
B (White)
A (Red)
C (Black)
C(Black)
Heat Shrinkable Tubing
Crimp and Solder Here
Lug tip
Heat Shrinkable Tubing
Heat Shrinkable Tubing
 T*
1
 (Yellow)
A (Red)
B (White) 
5 (0.2)
FEP Insulation Tubing 
(Black)
C (Black)
 T*
1
 (Yellow)
A (Red)
B (White) 
10
NOTE
Check that the insulation resistance between each 
wire including the inner shield is 10M or greater at 
500V DC. Ensure that both ends of the wires are 
disconnected (open-circuited) during the check.
NOTE
In case that the cable end fi nish 
parts assembly is necessary 
after delivery, contact your 
nearest Yokogawa sales offi ce 
or the sales representative 
from which you purchased the 
product. 
CAUTION
Do not touch the '' conductive layer" 
(black area covering the signal cables A 
and B) to the converter case, terminal, 
and other leadwires. If it is touched, 
operation of the converter may be 
incorrect. When the cable is terminated, 
remove the conductive layer properly. 
(B)
(C)
White
Black
(A)Red
Unit : mm
(approx. inches)
F0408.ai
60 
(
2.36
)
80 
(
3.15
)
20 
(
0.79
)
70 
(
2.76
)
Yellow
*1
(
T
)
 50 
(
1.97
)
Figure 4.7  End Processing Method of DYC Signal Cable for Detector