Instruction manual

Unpacking:
It is advised that two or more persons are involved
in the transfer of the packaged boiler from the van
to the point of delivery.
1 Once the packaged boiler has been
delivered, the outer carton is opened first.
Care should be taken when releasing the
straps. If a sharp implement is used make
sure the outer carton is not pierced and that
the implement is used in such a way so that it
may not cause personal injury. All sharp
objects must be covered or the blade
retracted after use and put away in a safe
place.
Lift the accessories tray out of the top of the
boiler carton and place in a safe place away
from the installation area. Installation and
user instructions are in this tray.
2 Lift carton up and away from the boiler.
Remove protective packaging from the front
of the boiler.
Remove protective bag from the appliance.
The flue adaptor is packaged at the base of
the boiler.
All packaging must be moved away from the
installation area to avoid a potential tripping
or slipping hazard.
At all times the correct method for handling
heavy objects should be strictly observed.
The unpacking of the appliance requires the
removal of the board support at the base of
the boiler. Instructions for this are on the
following pages.
UNPACKING THE BOILER
LIFTING AND CARRYING PRECAUTIONS:
• Lift only a manageable weight, or ask for
help.
When lifting or putting things down, bend
the knees, and keep the back straight
and feet apart.
Do not lift and twist at the same time.
Lift and carry objects close to the body.
Wear protective clothing and gloves to
protect from any sharp edges.
IIMPORTANT: All the previous Pre-Installation sections must be read
and requirements met before starting boiler or flue installation.
1
2
INSTALLATION
UNPACKING THE BOILER
INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER GREENSTAR DANESMOOR WALL MOUNTED OIL 12/18-18/25
8 718 681 134a (08.08)
19