Operating instructions
51
7 Operation
7.1 Starting the machine
Before the machine is started up, the main shutoff valve in
the fresh water supply line must be opened and the main
electrical switch supplying the machine must be turned on.
Turn the key switch 3 to position “I” (On).
The machine is now switched on and will heat up to
operating temperature (about 12 minutes).
During the heating-up phase the display alternately shows
the following:
LOCKED 11:21
20.04. ^
--Warm up--
When the machine has warmed up, the display shows the
following message:
READY
Pre-sel 01
11:21
20.04.
“READY”: The machine is ready for use.
“11:21”: Current time.
“20.04”: Current date.
“Pre-sel 01”: Only one brew is carried out for
each key press.
See page 56,
7.5.4 Quantity selection.
7.2 Filling the coffee beans hopper
To fill the coffee beans hopper 1 remove the hopper lid and
fill the hopper with coffee beans. Then replace the lid to
close the hopper. Each coffee beans hopper has a capacity
of approx. 1.1 kg.