2. Layout
Laying Out the Equipment
4 The unit will begin a series of internal and external tests. The LEDs on the top
of the unit indicate the current test and whether the unit passes or fails each
test.
2.5.4 Placing the BSU in the Field
The BSU is part of the backhaul configuration. See “3. Backhaul” on page 31 for
more information.
NOTE
See “D. LED Indicators” on page 100 for an explanation of the LED
status and error conditions.
If a WRU self test fails, the WRU will continue to the next test.
You can skip a self-test by tipping the WRU geophone down and then
returning it to the upright position (flat on the ground).