User's Manual

Preliminary
16 RT 1000 v1.0 Deployment Guide R01
© 2010-2011 Wireless Seismic, Inc. All rights reserved.
Layout
At the Site
To assemble the ground equipment:
1 Gather the equipment:
WRU or LTU
Antenna
Geophone
Batteries
2 Attach one or more batteries to the unit.
Steps TBD.
3 Attach the geophone to the unit.
Steps TBD.
4 Attach the antenna to the unit.
Steps TBD.
2.3.2.3 Place the Ground Equipment in the Field
This section describes the process to ready the ground equipment for interaction
with the central recording system (deployment).
To deploy the ground equipment:
1 Prerequisites:
The WRU or LTU is assembled with battery, geophone, and antenna
2 Pick up the unit and point the geophone connector end towards the ground as
shown in the following figure. All of the LEDs illuminate:
Image showing battery installation TBD.
Figure 2–4 Installing the Battery
Image showing geophone installation TBD.
Figure 2–5 Installing the Geophone
Image showing antenna installation TBD.
Figure 2–6 Installing the Antenna