B. The Contractor shall make his interface with the incoming primary
telecommunications cable(s) at the site boundary in the manner shown on the
Drawings.
Part 2 Products
2.01General
A. Except for those items as may be specified in Part 3 of this Section, refer to Part 2
of the various sections of the specification, Division 16, Electrical.
Part 3 Execution
3.01 Workmanship
Materials, products and equipment furnished by the Contractor, shall be installed and
all work shall be performed in a first-class workmanlike manner, in conformity with
the best trade practices and the printed directions of the applicable manufacturers; by
skilled workers equipped to produce satisfactory results; in a safe, substantial manner
so as to avoid undue stresses, rigid enough to prevent undue movement, so as not to
interfere with work of other trades and so as to preset a neat, orderly appearance and
to facilitate operating, servicing, maintaining and repairing.
3.02 Foundations and Supports
A. The Contractor shall provide concrete pedestals, bases pads, curbs, anchor blocks,
anchor bolts, slab inserts, hangers, channels, cradles, saddles, etc.., for installation
of equipment and apparatus shown on the drawings and specified in the various
sections of specification Division 16, electrical.
B. Concrete pads shall be 150mm high, unless otherwise indicated, complete with
steel reinforcing and necessary bolts, anchors, etc. Where concrete pad is set
directly on concrete floor, dowels in floor to tie base to floor shall be provided.
These pads shall be extended at least 100mm beyond the equipment outline on all
four sides.