PART 3 - EXECUTION
3.1 INSTALLATION
A. GENERAL
1. The engine and generator shall be properly aligned and mounted
on a common steel base through resilient mountings to prevent
vibrations. The whole set shall be fixed on the concrete slabs
through suitable number of adjustable spring type vibration
isolators. Foundation and other builder's work shall be as
recommended by the manufacturer and approved by the Engineer.
2. Except as may be described in this Section or shown on the
drawings carry out installation strictly in accordance with the
manufacturer's recommendation.
B. Control Boards
1. Run all outgoing cables from the generator to the control boards in
the floor trench as indicated on the Drawings.
3.02 PAINT WORK
A. Paint work of each set shall be of the highest quality to withstand the
worst weather conditions specified. All steel works such as tanks, pipes,
frames, louvers, ladders, platforms, etc.. shall be given two undercoats of
anti-rust paint and two enamel finishing.
3.03 SITE QUALITY CONTROL
A. Final Testing
1. The Engine manufacturer’s qualified representative in the presence
of the Engineer shall carry out testing at full load after completion
of installation.
2. If the above cannot be done then testing shall be done at the
manufacturer/supplier's premises at full load in the presence of the
Engineer. All arrangement and costs incurred by such a test shall
be responsibility of the Sub-Contractor.