Installation Manual

Tighten flange nuts to at least
15 ft-lb / 20.5 N-m using general
purpose anti-seize on threads.
Position WEEB-9.5 as shown.
WEEB will not create a ground
path in other orientations.
Tighten flange nuts to at least
15 ft-lb / 20.5 N-m using general
purpose anti-seize on threads.
Wiley Electronics LLC. 2006-2010

All Rights Reserved
East-West Formed Angles
If running wire outside of conduit and in or along the E-W members or ballast tray,
the E-W members and ballast trays must be grounded as shown below, or as
shown on the next page.
2
Use one WEEB-9.5 at every mounting point that joins the E-W formed angles to the
mounting bracket. Place the WEEB-9.5 on the formed angle with the legs pointing
down into the slot. The WEEB must be positioned perpendicular to the slot, to
ensure proper bonding when the hardware is tightened. Where ballast pans are
connected to the E-W formed angle, they may be connected to equipment ground
by using one WEEB-11.5 at one of the connection points.