User manual
Wide Bank 28 DS3 - Release 2.4 5
Guidelines
l Retrieve the facility to verify parameters and present state
l Retrieve the facility condition to verify normal operation (see Retrieve Condition on page 40)
l Retrieve the facility alarms to verify normal operation (see Retrieve Alarms on page 41)
Configure the next facility
l Repeat the above items to configure each of the remaining facilities
Test the facilities
l Follow standard practices to test each facility
l If desired, use the Diagnostics on page 32 and Loopbacks on page 34
Provisioning Existing Circuits
Configure the first facility
l Retrieve one of the facilities to verify parameters and present state
l The present state of the T3 facility is always in service and equipped (IS-EQ)
l Check the present state of T1 and E1 facilities to verify that the facility is available
l If necessary, enter or edit the facility parameters and place the facility in service
l Retrieve the facility to verify parameters and present state
l Retrieve the facility condition to verify normal operation (see Retrieve Condition on page 40)
l Retrieve the facility alarms to verify normal operation (see Retrieve Alarms on page 41)
Configure the next facility
l Repeat the above items to configure each of the remaining facilities
Test the facilities
l Follow standard practices to test each facility
l If desired, use the Diagnostics on page 32 and Loopbacks on page 34.
Available Test Functions
l Verify IP network connectivity to the Wide Bank with a PING command
l After login, verify normal Wide Bank response with the RTRV-HDR command
l Diagnose fans, E1, and T1 circuits with the DGN-{ENV|E1|T1} command
l Allow detection of loopback codes with the ALW-LPBK-{E1|T1|T3} command
l Send loopback codes with the CONN-LPBK-{E1|T1|T3} command
l Operate loopbacks with the OPR-LPBK-{E1|T1|T3} command