8.0 UNPACKING
Prior to unpacking, ensure pallet is set
on a level surface and proper PPE is
equipped by all personnel. Proper PPE
for unpacking includes but is not limited
to eye protection, cut-resistant gloves
and steel-toe footwear.
Cut the two green strips of banding
material with scissors. These strips are
under high tension and will snap when
cut. Eye protection is highly
recommended.
Lift the pallet lid and set away from
unpacking area.
Using a box cutter, carefully cut along
the corner from the top to the middle of
the box on the packing slip side. Ensure
the blade stays on the outside and does
not cut through the white corner
protectors.
After both corners have been cut, fold
the lengthwise side of the box halfway
down allowing easy access to the
modules. Cut the internal banding
material as well being careful to avoid
contact with the modules.
Peel back sides of box to allow additional
access to modules
.
(Optional) Apply no-residue tape across
the plastic corner clips to provide
additional support to stack as modules
are removed.
(Optional) Tape must reach at least 6
inches
down on opposite side of box to
maintain hold.
Remove white corner protectors.
Always wear Proper PPE when handling MSE Panels