Installation Guide
39 TriStar MPPT-600V-TR Operator's Manual
38
Installation
!
CAUTION: Risk of Tampering
The Ethernet Security settings switch does not block write commands to devices bridged via EIA-
485.
REMARQUE :
Le réglage des paramètres de réseau et des points de consignes personnalisés est toujours
activé par les connexions RS-232 et EIA-485. Le contacteur de sécurité Ethernet n’active/
désactive que la conguration à distance par TCP/IP.
!
PRUDENCE : Risque de tentative d’altération
Le contacteur des paramètres de sécurité Ethernet ne bloque pas les commandes d’écriture sur
les dispositifs reliés par EIA-485.
Step 10 - Grounding and Ground-Fault Interruption
WARNING:
The TS-MPPT-600V-TR is not provided with a GFDI device. This charge controller must
be used with an external GFDI device as required by the Article 690 of the U.S. National
Electrical Code for the installation location.
NOTE:
Conductors identied by the color combination green/yellow shall only be used for earthing
conductors.
AVERTISSEMENT :
Le TS-MPPT-600V-TR n’est pas fourni avec un dispositif GFDI. Ce contrôleur de charge
doit être utilisé avec un dispositif GFDI externe tel que requis par codes / règlements
locaux .
Use a copper wire to connect the grounding terminal in the wiring box to earth ground. Per NEC
690.45 and NEC Table 250.122, the minimum size for copper grounding wire is:
(1) TriStar MPPT 600V unit 60A 10 AWG ( 8 mm
2
)
OR, of the same, or greater, cross-sectional area as the PV wires.
Also follow any additional local grounding code / regulations that may apply.
The grounding terminal is identied by the ground symbol adjacent to the terminal and shown
below:
Do not connect the system negative conductor to this terminal. NEC requires the use of an
external ground fault protection device (GFPD). The TS-MPPT-600V-TR-GFPD affords this
protection, and installation is detailed in the GFPD-600V product manual. In tradtional GFDI
devices, the system electrical negative should be bonded through a GFDI to earth ground at one
(and only one) location. The grounding point may be located in the solar circuit or the battery
circuit.
WARNING: Risk of Fire
DO NOT bond system electrical negative to earth ground at the controller. Per NEC
requirements, system negative must be bonded to earth ground through a GFPD at only
one point.
AVERTISSEMENT : Risque d’incendie
NE LIEZ PAS le côté négatif du système à la mise à la terre au niveau du contrôleur.
Selon les exigences du CNE, le côté négatif du système doit être mis à la terre par un
GFPD à un seul point.