6. Transport/Unpack/Storage of PV Modules
6.1 Transportation and General Rules
Heliene recommend the modules be stored in its original packaging strapped to pallets until they reach the
destination of installation site.
Do not remove any strapping or packaging materials if the modules require secondary transportation/long-term
storage.
Do Not transport modules in an upright position, only transport them in box strapped to pallet as supplied by
Heliene Inc. on a level surface.
Load and Unload with a forklift avoiding hitting, banding, dropping or damage to the packaging.
Always keep electrical contacts clean and dry.
Do not Stand, Step on, Walk or Jump on the Modules.
Always set the modules onto surfaces bigger than the module perimeter size, as module weight must sit on the
aluminum frame ONLY. Please refer Dimensions of the module in Heliene Modules’ Specification Sheet.
6.2 Unpacking
Before unpacking, have module box in a level, dry area, free of excessive dust, debris. Read the unpacking
instructions carefully and follow the steps accordingly. This process requires two people minimum.
Cut the straps with blade or scissors, remove box top vertically and lift it over to the side.
Be carefully when removing the packaging, do not scratch the frame or glass.
Remove modules with two hands at each side, each person lifting on opposite ends. Never lift by Junction Box
Cables or Box.
Never leave a module unsupported or lean it on the mounting posts.
If there are modules left in the box after unpacking, the remaining modules shall be repackaged to prevent from
external damages. 26 modules maximum per pallet.
6.3 Storage
Store pallets of modules on a levelled surface, in a dry and ventilated room.
Pallet are not weatherproof and modules are not meant to be exposed to weather element until completely
unpackaged.
Store modules where there is not any potential of falling objects onto modules.
Stack only 2 boxes/pallets high at maximum, and never put any other materials on top of them.
7. Installation Requirements
7.1 Site Selection and Preparation
To maximize the power output, it is recommended to install PV modules at an optimized tilt angle. The module
must be facing towards the equator for optimum performance. Refer to standard solar photovoltaic installation
guides and incorporate other local requirements.
The module should not be shaded at any time of the day. Try to install the modules in a site where there is rare
shading throughout the year to minimize the chances of shading.
Never install the modules near the location/equipment where flammable gasses are generated.
7.2 Module Tilt-Angle
The tilt angle of the PV module is measured between the PV module and a
Horizontal ground surface. For different location or projects there are different
mounting angles, for maximum power output it is the best for PV modules to
face the sun directly. Ensure to comply with local regulations or follow