Technical information
OPERATION
20 December 2010 / M-SC6/8/10 / EN
3 OPERATION
3.1 GENERAL
The generating set is operational after full installation and
filling up with: fuel, engine lubricating oil and cooling liquid,
filling the starter battery with acid, connecting the battery
to earth and connecting the digital remote control panel.
Fig. 14:
3.2 OPERATING INSTRUCTIONS
3.2.1 Summarised operating instructions (daily
use)
Routine "pre-start" checks:
1 Check oil level (refer to fig. 14).
2 Engine cooling system (all valves open).
3 Power source selector switch (off/shore
power/generator power). Switch to power source
switch "OFF", or switch off all consumers in the usual
way.
4 Switch on battery switch (when installed).
5 Fuel valve: open.
Starting:
Push the start button to initiate the full automatic
starting procedure. You can monitor the procedure on
the display.
In operation checks:
1 Check for abnormal noise or vibration
2 Check the voltage
3 Check sea water flow at exhaust outlet
4 Power source selector switch (off/shore
power/generator power). Switch to power source
generator. If a Masterswitch is installed, this operates
automatically.
5 Before loading the generating set up to maximum,
have it run warm. Continuous load should be
restricted to 70 % of maximum load.
Stopping generator:
1 Switch off all electrical devices (consumers). If the
generating set has been running under full load for a
longer period, do not shut it down abruptly. Reduce
the electrical load to about 30% of the rated load and
let it run for approx. 5 minutes.
2 Press the STOP button.
3 Close the inlet sea water cock.
4 Switch to another AC power source, if available.
1
2
1 Maximum oil level
2 Minimum oil level