User guide

WHEATHEART - GRAIN AUGERS 4. OPERATION
4" GALVANIZED UTILITY 4.1. PRE-OPERATIONAL CHECKLIST
30645 R0 17
4.Operation
Operators must observe safety procedures at all times and follow the pre-opera-
tional checklist before each start-up.
4.1. PRE-OPERATIONAL CHECKLIST
Before operating auger each time, the operator must confirm the following:
All fasteners are secure as per assembly instructions.
Drive belt(s) are not frayed or damaged.
Drive belt(s) are properly adjusted and aligned.
Tube alignment is reasonably straight.
Intake area and discharge spout are free of obstructions.
Proper maintenance has been performed.
Inspect auger supports frequently.
4.2. AUGER DRIVE AND LOCKOUT PROCEDURE
4.3. OPERATING PROCEDURE
4.3.1. START-UP AND BREAK-IN
BREAK IN
1. Complete the checklist at the beginning of this chapter. If everything is
satisfactory, prepare for a 30-minute operation at half speed.
2. Correctly position the portable grain hopper secure it to auger with both
straps (where applicable).
Warning: Before continuing, please reread the safety information relevant to this section at
the beginning of this manual. Failure to follow the safety instructions can result in serious
injury, death, or property damage.
Drive Type Before Operation Lockout
Electric Motor
Before starting motor, ensure
motor is properly
grounded
pulley shields are in
place and secure
The electric motor should be equipped with a
main power disconnect switch capable of
being locked in the off-position only. The
switch should be in the locked position during
shutdown or whenever maintenance is
performed on the auger.
If reset is required, disconnect all power
before resetting motor.