SPS Box Mounting Instructions
For installation safety and security, the SPS power supply box shall be mounted into local
certified electric distribution box. Installer must use local certified AC cable at AWG18 and a
certified circuit breaker at 15A or 20A to disconnect main power from the SPS unit. And
then from distribution box, installer can direct the output cable from each SPS to local
pedestal at different sites. (find reference in
Interconnection between Smart Power
Supply and Pedestal
section.)
Installer can mount the SPS
power supply unit onto a
standard DIN46277-3 mount rail.
Mount Rail
1. Hang the SPS box
onto the upper flange
of mount rail.
2. Close up the bottom
of SPS box with the
mounting surface and
lock the lower flange of
mount rail.
Circuit breaker
at 15A or 20A
Certified
A
C cable
at AWG18
Reliable ground must be provided to the local certified electric
distribution box contains Power Supply, by AWG 18, according to
electric code.