User guide
17
6651-2221
Using the factory DIP-switch settings: …
Set DIP-switch S2:1 as desired. …
Connect The fibre link between the ODW-720-F1. …
Connect the power supply to both ODW-720-F1. …
After a few seconds the fibre link should be in operation, indicated by an active CH1 …
LED.
Connect the serial cables from PLC master and slave to respective ODW-720-F1. …
Frames from PLC master that are correctly received the ODW-720-F1 should be …
indicated by flashing TD LED.
Frames that are received via the fibre link will be transmitted to the PLC slave …
and indicated by flashing RD LED.
Replies from slave to master will be transferred and indicated in the opposite way. …
The point-to-point application is up and running. …
POWER CH 1
COM +VA +VB COM
POWER CH 1
COM +VA +VB COMTX RX TX RX
Start up guide, point-to-point application
Follow the steps below to get the unit up and running in a simple application.
Master Slave