Installation manual

IM 1029-2 Magnitude™ Frictionless Centrifugal Chillers Model WMC 47
Prestart System Checklist
Yes No N/A
Chilled Water
Piping complete ................................
........................................................
Water system filled, vented ......................................................................
Pumps installed, (rotation checked), strainers cleaned .............................
Controls (3-way, face and bypass dampers, bypass valves, etc.) operable
Strainer installed at evaporator inlet .........................................................
Water system operated and flow balanced to meet unit design requirements
Condenser Water
Cooling tower flushed, filled and vented .................................................
Pumps installed, (rotation checked), strainers cleaned ............................
Strainer installed at condenser inlet ..........................................................
Controls (3-way, bypass valves, etc.) operable ........................................
Water system operated and flow-balanced to meet unit requirements .....
Electrical
Power leads connected to the unit power panel(s) ...................................
All interlock wiring complete to control panel and complies with specifications
Pump starters and interlock wired ...........................................................
Cooling tower fans and controls wired ....................................................
Wiring complies with National Electrical Code and local codes .............
Condenser pump starting relay (CWR) installed and wired ....................
Miscellaneous
Relief valve piping complete ...................................................................
Thermometer wells, thermometers, gauges, control wells, controls, etc., installed
Minimum system load of 80% of machine capacity available for testing
and adjusting controls .............................................................................
Control wiring between multiple units, if applicable.........................................................
Note: This checklist must be completed and sent to the local Daikin Factory Service location two weeks prior
to start-up.