User Documentation
7.3  Commissioning the UR67 module
 ▶ Start the SIMATIC Manager.
 ▶ To set up a new project, click File/New.
The “New Project” window opens.
 ▶ Enter a name for the new project (e.g. UR67_Station1) 
and click OK.
The new project is displayed in SIMATIC Manager.
Creating a new project
Adding a control unit type
 ▶ Select the project in SIMATIC Manager.
 ▶ Select the control unit type VIA Insert/Station  
(e.g. SIMATIC 300).
Adding a station
 ▶ Double-click on the project name so that the station 
(SIMATIC 300) is displayed below in the directory tree.
 ▶ Click on the station (SIMATIC 300).
 ▶ Double-click Hardware on the right-hand side of the 
window.
The “Hardware Conguration” window opens.
Hardware configuration
 ▶ The device catalogue is displayed on the right-hand side 
of this window. If this does not occur, open the catalogue 
via View/Catalogue.
Adding a prole rail
 ▶ In the catalogue, choose the profile rail (e.g. SIMATIC 
300/RACK-300).
Choosing a profile rail
 ▶ Double-click on the profile rail or drag it to the left-hand 
side of the window using the mouse.
7 Commissioning | Commissioning the UR67 module
382484950000/00/03.2016 Manual UR67-PROIFBUS