User's Manual

Table Of Contents
Installation_________________________________________________ Boomer II User Manual & Integrator’s Guide
Copyright Wavenet Technology © November 2003 50 BM210012WT37
Power Down Diagram Callouts
1 HOSTPWR_ON is de-asserted from the host/terminal to the
modem.
Important: The power rail must be present for up to ten seconds
(typically two seconds) after HOSTPWR_ON is de-asserted for the
deregistration process to complete orderly.
2 The modem starts the soft shutdown process. The battery status
indicator pulses quickly until the shutdown steps are complete.
The modem initiates the deregistration process from the network
and upon completion de-asserts DSR and DCD. DCD signifies
network detachment, and DSR shows the modem’s readiness state.
3 After deregistration, the internal modem CPU power-on signal is de-
asserted. This deactivates the internal modem power rail to the
radio.
4 At this point you can optionally de-asset HOSTPWR_ON signal to
the modem and assert the HCRESET line to the modem.