Installation Instructions

6
Retro-Fit Installations
1.) Cut the existing concrete slab and form a cavity which will enable a 4"
concrete pour below and around the Dead Level
®
system.
2.) Cut 2x4’s at least 30" in length to span the cavity. Align the 2x4’s with the
frame cross bars, and drill 1/2" holes corresponding to the tapped holes in
the cross bars.
3.) Insert an approx. 1/16" thick shim between the frame and the 2x4’s to
ensure the trench drain will sit below the nished grade. Attach the 2x4’s
to the cross bars with 3/8" x 4 1/2" (minimum) bolts and washers.
4.) Securely anchor the 2x4’s to the surrounding slab to prevent shifting or
oating during the pour.
5.) Once the concrete is set, remove the 2x4’s and complete any unnished
areas with concrete.
6.) Install the grates, lockdowns, and construction covers.
Non-Sloped Dead Level
®
S, Dead Level
®
SP, Dead Level
®
Z System Installation
Note: Systems installed above grade must be fully encased in a concrete
slab, and waterproofed to prevent leak-through. Please contact your
Watts representative for above grade installations.
1.) Dead Level
®
non-sloped systems are designed to be installed with the
frames attached to the channels; do not separate the channels from the
frames. All sections are the same depth, and can be installed in any
sequence without regard to the direction of ow.
End Cap
Standard Section
End Cap
Standard Section
Flow
Flow
FIG. H
Standard Section
Standard Section
End Cap
End Cap
Flow
Flow
FIG. I