Operating instructions

7
Installation
8
9
0622
Electrical installation
Although the machines are fitted with thermal
overload in the motor windings and separate fuse
for the control circuit, a separate three-phase
circuit breaker must be installed for all three-
phase machines.
For proper overcurrent protection, check the data
plate at the rear of the machine. Also consult
local electrical code for special requirements.
Connect L1, L2, L3 and ground wires according
to the markings of the terminal block. The cable
is to hang in a large loose loop, supported by the
clip of the terminal block.
To ensure proper operation the drum must
rotate counter-clockwise (seen from the front)
during extraction. If the drum rotates in the wrong
direction interchange line L1 and L3 at the power
connection terminal.
Check the incoming power for a high voltage leg.
If present, connect that line to L2 on the terminal
block.