Datasheet
Release Notes - New Features included in Release 2.4.0
Page 38 of 89
• QSCM has been modified to allow separate sets of codes to be defined for specific items or
product groups.
• QSTM has been changed to allow input of the resource number associated with the test.
• QSBC and QSBS have been modified to display and record new warning indicators against
a V type test result which falls within the maximum/minimum but outside the new limits
defined on QSCL.
• QSEQ, QSTE and QSTQ have been modified to show these new values.
• QSBP and QSPW cannot be used with hierarchies/limits.
• QSPR has been modified to print test results sheets based on characteristics derived from a
hierarchy.
• QSTT has been modified to transfer test results derived from a hierarchical test.
• QTTX has been modified to record text against hierarchical tests.
• QSTR has been introduced to allow enquiry on tests for a specific resource.
• QSVH now shows the type of quality specification (group or normal).
• CAPR has been modified to output the new quality details to the white paper printing
routines.
• LTRE has been modified to determine which QA specifications in a hierarchy are relevant.
Manual Set-Up Procedures
The QSMG transaction is used to enable the use of the new facilities.
4.2.10 Production Scheduling (PMPL)
4.2.10.1 Subcontract Control (SR2707)
The existing subcontract control facilities within TROPOS have been extended to provide a greater
degree of control over the management and costing of subcontract activities.
The Resources, Products and Processes Module (RPPM) will allow the definition of a process stage
as a subcontract activity, and allow definition of preferred and multiple alternative subcontractors
with an estimated cost rate and a standard lead-time for each.
Once a Production Order has been raised for such a product and process, the required subcontractor
may be selected or confirmed for a subcontract or normal internal activity. The selection process
will automatically generate a sales transfer order for the despatch of any WIP material and free
issue ingredients that are required to be sent to a subcontractor.
A Goods Subcontract purchase order can be either automatically or manually raised for the receipt
of the returned subcontract materials. Once the materials have been received back from the
subcontractor there is an inspection mechanism which allows the goods to be inspected, and then
released to the relevant production order process stage for completion of production.
The following facilities are available to control the production planning and receipt of a subcontract
activity.