- 1 Foreword
 - 2. Safety Information
 - 2.1 Operating Safety
 - 2.2 Service Safety
 - 2.3 Operator Safety while using Internal Combustion Engines
 - 2.4 Towing Safety
 - 2.5 Reporting Trailer Safety Defects
 - 2.6 Label Location
 - 2.7 Safety and Operating Labels
 - 3. Operation
 - 3.1 Control Panels
 - 3.2 Generator Monitoring
 - 3.3 Engine Monitoring
 - 3.4 Engine Shutdown Faults
 - 3.5 Current Overload Fault
 - 3.6 Application
 - 3.7 Voltage Selector Switch
 - 3.8 Emergency Stop Switch
 - 3.9 Main Line Circuit Breaker
 - 3.10 Engine Start Switch
 - 3.11 Voltage Adjustment Rheostat
 - 3.12 Warning Light
 - 3.13 Connection Lugs
 - 3.14 Ground Connection
 - 3.15 Convenience Receptacles
 - 3.16 Remote Run Terminal Block
 - 3.17 Panel Door Interlock Switch
 - 3.18 Terminal Connections
 - 3.19 Before Starting
 - 3.20 Manual Start-up
 - 3.21 Running the Generator
 - 3.22 Engine Power Correction Factors
 - 3.23 Shutting Down Generator
 - 3.24 Cold Weather Start-up
 - 3.25 Lifting
 - 3.26 Overnight Storage
 - 3.27 Long-term Storage
 - 3.28 Automatic/Remote Start-up
 - 3.29 Remote/Transfer Switch
 - 3.30 Towing
 - 4. Maintenance
 - 4.1 Periodic Maintenance Schedule
 - 4.2 New Machines
 - 4.3 Resetting the Periodic Maintenance Timer
 - 4.4 Air Cleaner
 - 4.5 Engine Lubrication
 - 4.6 Engine Coolant
 - 4.7 Trailer Maintenance
 - 4.8 Troubleshooting Automatic Shutdown
 - 4.9 Wire Colors
 - 4.10 Generator and Receptacle Wiring
 - 4.11 Trailer Wiring
 - 4.12 G 50/G 70 Engine Wiring
 - 4.13 G 85 & G 70 w/ECU Engine Wiring
 - 5 Factory-Installed Options
 - 5.1 Block Heater
 - 5.2 Fuel/Water Separator
 - 5.3 Electronic Governor
 - 5.4 LCD Strip Heater
 - 5.5 Low Coolant Shutdown
 - 5.6 Lube Level Maintainer
 - 5.7 Temperature-Activated Shutters
 - 5.8 Lockable Battery Disconnect
 - 5.9 Wiring Diagram
 - 5.10 Wiring Diagram Components
 - 5.11 Cam-Lock
 - 5.12 Containment System
 - 6. Technical Data
 - 6.1 Engine Data
 - 6.2 Generator Data
 - 6.3 Trailer and Skid Data
 - 6.4 Dimensions
 

Maintenance G 50/G 70/G 85
wc_tx000484gb.fm 48
4.2 New Machines
4.2.1 Run generator at least 60–100% of continuous load for the first 100
hours.
4.2.2 Change engine oil and replace oil filter after the first 50 hours.
4.3 Resetting the Periodic Maintenance Timer
After maintenance has been performed on the generator, it is
necessary to reset the periodic maintenance timer. 
• If the periodic maintenance timer is at zero, press the ENG. HRS
switch UP and hold for 10 seconds until the “TIME TO SERVICE”
resets to 250 hours.
• If the service time is greater than zero (maintenance was performed
prior to the timer running out) press and hold the ENG. HRS switch UP
and hold for 30 seconds. This will reset the “TIME TO SERVICE” to
250 hours.