Operator`s manual
  PUREHEAT™ HYDRONIC AIR HEATER OPERATOR’S MANUAL – SECTION 2 
2- 4  © 2006 Ground Heaters, Inc.  V. 2, Rev. 09/01/06   
2-4
2-3 
2.2.3  Unloading HX100 Heat Xchangers
TM
1.  OPEN the Rear Doors and remove the aluminum Ramp from the storage location above Xchangers. 
2.  Position the Ramp onto the Ramp Alignment Pins to unload either the left side, right side or the 
middle section HX100s. (Photo 2-2) 
NOTE: Each HX100 Heat Xchanger
TM
 is equipped with 
wheels, Lifting Bail and Lift-Up Handle. 
3.  Position the HX100s inside the building per your 
heating plan. (Refer to Appendix C-1, PUREHEAT 
APPLICATION LAYOUTS.) 
NOTE:  Each HX100 Heat Xchanger
TM
 must be connected to 
a separate
 15 amp. 120 volts AC 60 Hz electrical 
circuit. Use 12-3 gauge extension cords of no more 
than 100 ft (30 m) in length. 
4.  Momentarily turn the Fan Switch ON to test Fan operation then turn the Fan Switch OFF. 
2.2.4  Unloading HX50 Heat Xchangers
TM
1.  OPEN the Rear Doors and unload the HX50s. (Photo 2-3) 
NOTE: Each HX50 Heat Xchanger
TM
 is equipped with a Lifting Bail and  
Handles. The HX50 Heat Xchangers
TM
 weigh approximately 70 lbs and 
can be lifted by one individual. 
2.  Position the HX50s inside the building per your heating plan. (Refer to 
Appendix C-1, PUREHEAT APPLICATION LAYOUTS.) 
NOTE:  Each HX50 Heat Xchanger
TM
 must be connected to a separate 15 amp. 
120 volts AC 60 Hz electrical circuit. Use 12-3 gauge extension cords 
of no more than 100 ft (30 m) in length. 
3.  Momentarily turn the Fan Switch ON to test Fan operation then turn the 
Fan Switch OFF. 
2.2.5  Heat Transfer Fluid (HTF)
  OPEN the Side Doors and Latch them to the Door Tiebacks 
1. Verify Heat Transfer Fluid (HTF) level is between MIN and MAX lines on the Sight 
Gauge Decal located on expansion tank above Hydronic Heater. (Photo 2-4) If fluid 
level is not above MIN level, refer to Section 4.1, ADDING HEAT TRANSFER FLUID, 
to correct before attempting to start the Burner or HTF Pump. 
If HTF temperatures are below -15ºF (-26ºC), pre-heat the HTF and 
Pump housing before turning the Pump ON. 
2.2.6 Switch Positions
(Refer to Appendix A-2.) 
Verify the MAIN BREAKER 1, MAIN BREAKER 2, PUMP, BURNER, CAB LIGHT and 
HOSE REWIND Switches are in the OFF position on the Main Control Panel. 
2-2
 !










