Installation RF-Orchestra!™ Transmitter Installation and Operation
4-6 6880493G02-C July 2000
Recommended Parts
The following table lists the recommended parts for installation. These parts are not included
as part of the RF-O! paging station shipment and must be procured locally (see Table 4-3).
Cabinet Installation
The following information provides procedures for installing the equipment cabinets at a site
selected by the paging service provider. The procedures assume that all prerequisites are
satisfied and the site is ready for equipment installation. All antenna cables, power outlets,
and ground wires must be in place before installing the RF-O! paging station cabinet.
Cabinet
All equipment cabinets are equipped with casters. The two front casters have locks that must
be unlocked before moving the cabinet. Relock the casters after positioning the cabinet.
Table 4-3: Recommended Parts for Installation
Part Type/Size Manufacturer Where used
Anchor kit #2100-13 Hendry Cabinet floor anchors
Colored vinyl tape Red, black, green,
brown, yellow, and white
Locally procured Wire identification
Ground cables #2 AWG stranded
copper [(Cu) green]
#6 AWG stranded
copper [(Cu) green]
Locally procured
Locally procured
Cabinet grounding
Cabinet grounding
Ground wire #4 AWG bare solid Locally procured Cabinet grounding
Split nuts No specific model
recommended
Locally procured Join grounds
Lifting eyes Locally procured Lifting cabinets
Floor anchor kit Locally procured Anchoring cabinets