INSTALLATION INSTRUCTIONS
- Put the blender in place and anchor it down to the floor (if blender consists of several frames set the
bottom and assemble the machine).
- Install vacuum chambers and connect vacuum and material lines.
- If installing WSB100, attach vacuum chamber extensions to top plate prior to installing vacuum
chambers. Be sure to use mounting bolts provided which do not extend below top mounting plate.
Lower material bins are removable and must slide freely.
- Attach the weigh chamber to the load cell.
- Install rubber boot and the clamp. Make sure the boot is 1/2” above the safety bars in the mixer.
- Connect the air tubes.
- Make sure the ground wire is connected between weigh chamber and the frame.
- Connect material lines to the vacuum take off tubes on the mixer barrel.
- Bring 30A 480VAC service from MCC to the starter disconnect. Make sure the true GROUND is
connected to the blender’s frame. If no true ground available use ground rod to create one. Blender
consumes 2A 480VAC.
- Bring the control wiring from vacuum loader control panel to the blender junction box (see blender
and vacuum loader wiring diagram):
• demand signal for bin #1 to terminal “A”
• demand signal for bin #2 to terminal “B”
• demand signal for bin #3 to terminal “C”
• demand signal for bin #4 to terminal “D”
• demand signal for bin #5 to terminal “E”
• demand signal for bin #6 to terminal “F”
• The HOT wire #3 to terminal 101.
- If the vacuum control valves are installed on the blender connect the vacuum loader control panel
neutral #2 to terminal 200 and
• signal wire for valve on bin #1 to terminal 161
• signal wire for valve on bin #2 to terminal 162
• signal wire for valve on bin #3 to terminal 163
• signal wire for valve on bin #4 to terminal 164
• signal wire for valve on bin #5 to terminal 165
• signal wire for valve on bin #6 to terminal 166