Installation guide

40 Acme Packet 6100 Hardware Installation and Maintenance Guide
2. Line up the painted side of the stationary rail with an appropriate mount
point on the front of the equipment rack.
Figure 4 - 52. Aligning the Slide Rail Front Mount Point in a Square-Hole Rack
3. For each of the two holes in the slide rail flange, place a #10-32 screw
through the mounting spacer, then through the slide rail flange, and
finally through the square hole in the rack rail.
Mounting Spacer
10-32x5/8” Screw
Slide Rail Flange
Nut Bar
Square-Hole Rack
Figure 4 - 53. Attaching the Slide Rail to a Square-Hole Rack
4. Hold the nut bar behind the front rack rail.
5. Using a #2 Phillips head screwdriver, tighten the screws to secure the slide
ra
il to the equipment rack. Do not completely torque the screws; leave a
small amount of play at this time.
Figure 4 - 54. Installed Slide Rail in a Square-Hole Rack - Front Mount Point