Specifications
Manual # 016-0159-894 Rev H 01/07
319
5. Note the ‘Ttl Vol’ (total volume) column and the numbers for each node.
6. Turn the boom switches and the Master switch ‘On’.
7. With a small jumper wire (or paper clip), short between the 2 o’clock and
6 o’clock sockets with a ‘short-no-short’ motion. Each time contact is made,
the Ttl Vol number should increase by increments of 1 or more.
8. If the Ttl Vol total does not increase, remove the section of cable and repeat
the test at the connector that is the next closest to the node. Replace the
defective cable as required.
9. Verify the pin connection and voltage from the previous chart.
10. If all of the cables test ‘good;, replace the Flow Meter.
Remember: After testing is complete, re-enter the correct
Meter Cal before starting application.