Technical data

6
8.3 Inspection of the installation
Before the commissioning, the future operating or-
ganisation along with the installing companies
(heating engineer & electrician) are obliged to in-
spect the installation for the following points:
1. Exhaust gas port connected to the exhaust
gas line on the chimney.
2. Chimney completely installed with clear cross
section all the way through.
3. Safety valve installed on the boiler and/or
boiler forward flow.
4. Thermal run-off safety valve connected to the
cold water network.
5. The sensor for the thermal run-off safety valve
is situated in the dipping shell.
6. The sensor for the temperature-limiting safety
switch is situated in the dipping shell.
7. The extinguishing water tank on the feed au-
ger is filled with water.
8. The sensor for the extinguisher valve is
mounted tight on the pipe for the feed auger.
9. The expansion tank is connected.
10. The conveying systems are installed between
the boiler and the material storage unit.
11. The facility is filled with water.
12. Material to be burned is stored for the test op-
eration.
13. The safety limit switch is installed on the door
to the material storage site (if there is a walk-
through door).
14. The control system is connected to the power
supply network.
15. The motors, switches and sensors are electri-
cally connected.
Do not put the facility into operation over-
hastily without the presence of a specialist
from KÖB Holzfeuerungen GmbH or another
trained specialist.
In case of damage, you would lose your war-
ranty claims.
Inspected on . . . . . . . . . . . . . . . . . . . . . . . . . . . .
By . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Signature . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8.4 Commissioning and handover
A competent contact person from the operating or-
ganisation's side must be present for the commis-
sioning and handover.
The heat dissipation from the boiler plant has to be
assured by the operating organisation or by the
heating engineer.
The heating engineer has to confirm that an in-
spection of the installation has been carried out
positively by handing over these signed Installation
Instructions.
Complying with these Installation Instructions and
also following the Operating Instructions, you will
be provided with heat from wood in a safe and
convenient fashion.
KÖB Holzfeuerungen GmbH thanks you for the
trust you have shown in us.
These Installation Instructions should be kept
near the facility on a permanent basis.