8.3 Inspection of the installation
Before the commissioning, the future operating organisa-
tion along with the installing companies (heating contractor
& electrician) are obliged to inspect the installation for the
following points:
1. Exhaust gas port connected to the exhaust gas line on
the chimney.
2. Chimney completely installed with clear cross section
all the way through.
3. Safety valve installed on the boiler and/or boiler for-
ward flow.
4. Thermal run-off safety valve connected to the cold
water network.
5. The sensor for the thermal run-off safety valve is situ-
ated in the dipping shell.
6. The sensor for the temperature-limiting safety switch
is situated in the dipping shell.
7. The extinguishing water tank on the feed auger is
filled with water.
8. The sensor for the extinguisher valve is mounted tight
on the pipe for the feed auger.
9. The expansion tank is connected.
10. The conveying systems are installed between the
boiler and the material storage unit.
11. The facility is filled with water.
12. Material to be burned is stored for the test operation.
13. The safety limit switch is installed on the door to the
material storage site (if there is a walk-through door).
14. The control system is connected to the power supply
network.
15. The motors, switches and sensors are electrically
connected.
Do not put the boiler plant into operation over-hastily with-
out the presence of a specialist from Viessmann or another
trained specialist.
In case of damage, you would lose your warranty claims.
Inspected on . . . . . . . . . . . . . . . . . . . . . . . . . . . .
By . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Signature . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8.4 Commissioning and handover
A competent contact person from the operating organisa-
tion's side must be present for the commissioning and
handover.
The heat dissipation from the boiler plant has to be assured
by the operating organisation or by the heating engineer.
The heating contractor has to confirm that an inspection of
the installation has been carried out positively by handing
over these signed Installation Instructions.
Complying with these Installation Instructions and also fol-
lowing the Operating Instructions, you will be provided
with heat from wood in a safe and convenient fashion.
Viessmann Manufacturing Company Inc. thanks you for the
trust you have shown in us.
These Installation Instructions should be kept near the facil-
ity on a permanent basis.