Install Instructions
Table Of Contents
- About this Document
- Disclaimers
- Product Information
- Viega Manifolds
- Viega PureFlow Tubing
- Viega PureFlow Fittings
- Viega PureFlow System Design Considerations
- Water Service Installation
- Installing the ManaBloc
- Mounting the ManaBloc
- Installing Manifold Distribution Lines
- Installing the Viega PureFlow PEX Tubing System
- Fastening the Viega PureFlow System
- Installing Viega PureFlow Fittings
- Pressure Testing Viega PureFlow Systems
- System Disinfection
- Installer Checklist
- Limited Warranty
Mounting the ManaBloc
44 of 88
IM-PF 724596 1021 PureFlow Water System (EN)
9 Mounting the ManaBloc
Where space permits, Viega recommends mounting the ManaBloc
on a surface rather than between studs for ease of accessibility and
replacement should a dierent ManaBloc port conguration be desired in
the future.
9.1 Mounting Between Studs with Mounting Straps
Dimensions in these instructions are for 16" stud centers and must be
adjusted for other stud spacing.
Once the general location of the ManaBloc has been determined (see "8.2
Location" on page 39), the ManaBloc may be mounted to a suitable
surface between a pair of adjacent studs. For 16" stud spacing, the
mounting straps (part number 45716) can simplify installation.
Additional Tools and Materials
■ Electric Drill
■ #2 Phillips Head Screwdriver
■ Pencil or Pen
■ Permanent Marking Pen*
■ Framing Square
■ Tape Measure
■ ¾" and 1¼" Wood Drill Bits
■ Wood or Drywall Screws - ½" or longer
■ ½" or ¾" Plywood - when ush mounting ManaBloc
* Optional
1. Lay the ManaBloc, plastic brackets down, on a suitable at surface that
is large enough to accommodate the full length of the ManaBloc. Place
a mounting strap under each plastic mounting bracket (located at the
top and bottom ends of the ManaBloc). Attach the plastic mounting
bracket at one end of the ManaBloc to the two outer center holes of a
mounting strap using the provided self-tapping pan-head screws. The
screw heads must be on the accessible side of the mounting strap.
Repeat at the other end of the ManaBloc. Tighten screws securely.
2. Standing behind the stud wall, measure up from the oor and make
a mark on the back of one of the studs to represent the top of the
ManaBloc (see illustration).
This mark should be between four feet and six feet from the oor but
may be at any height, provided the height will allow all valves on the
ManaBloc to be accessible. With a framing square or level, transfer
and mark the noted height on the other stud.
Measure up from the floor while standing
behind the stud wall. Mark a location for
the top of the ManaBloc.
4' to 6'
from oor