Install Instructions
157
IM-PR 566442 1114 (Design Manual)
Appendix D In-Slab Systems
B.1 Introduction
In-slab systems are an excellent choice for garages, workshops, basements, thin-slab installations and
any other application where slabs are 10,000 ft
2
or less. For larger installations, consider specification of
Climate Mat.
B.2 Typical cross sections
Installers may select from a variety of fasteners when installing in-slab systems, including Rapid Grid,
Snap Panel, wire mesh clips, plastic zip ties, U-channels, plywood staples and foam staples. Typical cross
sections are shown below.
In-slab systems must maintain at least ¾" of concrete between the top of the tubing and the top of the
slab. If installing tubing in a thin-slab, the minimum depth of the slab must be at least 1½". Be sure to
coordinate with the person responsible for control cuts or joints to prevent tubing from being damaged
after the pour, if the tubing is to be set high in the slab.
4" Concrete Slab: Minimum ¾" height
of concrete over ViegaPEX Tubing
R-5 Edge Insulation:
Refer to local code for
insulation requirements.
Rapid Grid:
Check with local code to see if Rapid
Grid is an acceptable vapor barrier.
R-10 Insulation:
Please reference local code for minimum
insulation requirements. (Ensure compression
rating is suitable for application.)
Gravel
Compact Subgrade
9" Spacing (per design)
ViegaPEX Tubing
Figure B-1a
Section through slab on or below grade installation using Rapid Grid