Install Instructions
149
IM-PR 566442 1114 (Design Manual)
Step 2:
Because most rooms are not perfectly square, lines need to be chalked to ensure proper layout of the
Climate Panels.
Begin by chalking a line along the wall where the first row of panels will be laid out. The line should be 7¼"
from the wall.
Next, chalk lines along the walls where the U-turn strips will be laid out. One way to ensure that the chalk
lines are perpendicular to each other is to use the right triangle rule (a
2
+b
2
=c
2
) also known as the 3, 4, 5
triangle.
4'
3'
Intersection
of chalked lines
must equal 5'
Snap chalk lines along the walls
with a distance of a U-turn strip;
width is 7" then add ¼"
Note:
Make sure oor is free of anything that
would inhibit the Climate Panels from
laying down at (screws, woodchips,
dried plaster, damaged plywood, etc.).
Mark out the area that
doesn’t require oor heating
such as kitchen cabinets.
This line is for the rst row
of Climate Panels. Make
sure the Climate Panels
are laid perpendicular to
the U-Turn Strips, which
may not be parallel with
the wall.