Assembly Instructions:
Numbers in parentheses correspond to parts numbers in the exploded parts diagrams on pp. 3-5.
Step 1: Create a foundation for the jib. The necessary minimum foundation requirements for each JIB-FM model
crane are provided in the diagrams and table below. When the foundation is adequately cured, install eight (8)
7
/
8
”
jam nuts on the anchor bolts. Wind them to the surface of the foundation. Level across the jam nuts by
raising/lowering specific nuts as necessary to make all of the nuts level. Then, fill the center of the bolt pattern
(see “Overhead View of Foundation” diagram below) with grout, e.g. Morta Mix. The top of the grout pedestal
should be level with the tops of the jam nuts.
Step 2: Set the mast on the foundation. Align the bolt holes in the mounting plate with the anchor bolts and
carefully lower the mast onto the leveling nuts. Install
7
/
8
” lock nuts on the anchor bolts but leave them loose.
Plumb the mast at 90° increments, i.e. check the vertical levelness of the mast at 4 locations equally spaced
around the circumference of the mast. Adjust the leveling nuts as necessary to fine tune mast levelness; then
tighten the lock nuts against the mounting plate.
Mortar pedestal
(1” high)
Mast
Concrete
foundation with
reinforcing bars
A
4”
C
B
5
/
8
” reinforcing rod
3
/
4
” reinforcing rod
Reinforcing rods ~12” centers
on both sides
Model A B C D
JIB-FM-3 18” 15” 42” 14
1
/
2
”
JIB-FM-6 24” 19” 46” 14
1
/
2
”
JIB-FM-10 30” 23” 50” 17”
JIB-FM-20 30” 23” 60” 17”
JIB-FM-40 48” 41” 72” 24”
7
/
8
” anchor bolts with J
hook (only one shown in
diagram; 8 required).
Threaded ends of
anchor bolts must project
~5” above the surface of
the foundation. Bolts must
be embedded to depth “B”
in foundation.
C
C
Overhead View of Foundation
Anchor
bolt hole
Mounting
plate
Mounting plate
at bottom of
mast
Mortar pedestal in
center of bolt pattern
5”
D
D