Unit Identification Information
Project: __________________________________________
Model Number: ___________________________________
Serial Number: ____________________________________
Tag: _____________________________________________
Jobsite Contact: ___________________________________
Job Name:________________________________________
Job Address: ______________________________________
Telephone: _______________________________________
Email: ___________________________________________
IMPORTANT
Complete this form for each unit and email, fax or mail to Venmar CES immediately after start-up to validate warranty
and to provide valuable information for personnel performing future maintenance or for factory assistance to address
below.
Read the Installation, Operation and Maintenance Instructions Manual before proceeding.
Leave a copy of this report with the owner and at the unit for future reference and permanent record.
To ensure proper operation of each unit qualified personnel should perform the start-up, complete the checklist and
report.
All units are factory run tested. Blowers and heat wheel are set up to run correct when power is connected. If any
blower is running backwards disconnect power. If there is a negative pressure in the space and an exhaust discharge
damper is missing or not closing properly, the fans with single-phase motors could be rotating in the wrong direction
before the power is turned on and may not correct itself. Check the exhaust damper is present and dampers are closing
properly or take corrective action before proceeding.
Table G1: Pre Start-up Checklist
Checklist Item Yes N/A
1 Is the electrical disconnect set to the ‘Off’ position?
2 Have shipped loose parts, obstructive packaging, objects, tie downs on fans been removed?
3 Are fans and motors rotating freely?
4 Are air filters installed, clean or replaced?
5 Are damper and linkages free of movement?
6 Is ductwork connected and complete?
7 Are condensate drain connections trapped, installed correctly and filled?
8 Are all shipped loose or field supplied components correctly installed and wired?
9 Has power supply and control wiring been inspected and approved by the Local Authorities?
10 Have factory and field wiring connections been checked and tightened?
11 Are all fuses properly installed in holders?
12 Is voltage at the disconnect switch within 10% of nameplate?
13 Are field piping and venting installation and connections for heating and cooling options completed and tested?
14 Have all thermostat setpoints been checked and adjusted?
VCES-HRV-IOM-1C – HRV600i, HRV700i, HRV1200i