To set up the CAP with the default configuration, use the steps described below:
1. Ensure that your CAP site has been prepared to support the CAP requirements,
including CCU antenna structures, power, grounding, and lightning protection.
WARNING!
This system must be professionally installed. Antennas and
associated transmission cable must be installed by qualified
personnel. WaveRider assumes no liability for failure to adhere
to this recommendation or to recognized general safety
precautions.
2. Reconnect the Exide 5119 UPS battery. Refer to
Reconnecting the UPS Battery After
Shipping
on page 9.
3. Plug the CAP UPS power cable into a 110 or 220 V AC power source using the
provided cable.
4. Set up your backhaul equipment and connect to the CAP. Refer to
Setting up your
Backhaul Equipment
on page 11 for more information.
After you have set up the CAP, the next step is to set up the NAP. Refer to
Setting up the NAP
Using the Default Configuration
on page 12.
2.1.1 Reconnecting the UPS Battery After Shipping
The Exide 5119 UPS is shipped with the battery bank disconnected and the rear breaker on
the rear power distribution bar in the OFF position. Reconnect the battery and place the
power switch to the ON position. Complete the following instructions before powering up the
unit.
WARNING!
The UPS is capable of generating sufficient voltage to cause
bodily harm. Use extreme caution when working with high
voltage equipment.