User`s manual

-
~hort~Pc setup
The short SPC setup and operation method enables you to
specify a few SPC parameters in a short setup record, then
run SPC operations using that record. You need little or no
experience with statistical process control to use this setup
option.
Using the Short SPC Setup Method
Here is the procedure for using the short method of SPC
setup and operation:
Your Action
Return to the Main Menu, if
you have not already done
so.
Press the “Y key to
highlight the Statistical
-
Process Control option,
then press the ENTER key.
Press the “s” key twice to
highlight the Short SPC
Setup Menu option, then
press the ENTER key.
Comments
When you press ENTER, the SPC Setup Menu should
appear on the display, as shown in Figure 8.3 (page 8-10).
(If the SPC Setup Menu does not appear, it was not selected
as the default setup menu in the Program Configuration
Screen. If this is the case, refer to Chapter 9, Program
Configuration Option, for information about selecting the
SPC Setup Menu as the default setup menu.)
When you press ENTER, the Short SPC Setup Menu
appears on the display, as shown in Figure 8.6 on page
S-18.
Note that the SPC option is highlighted when the Short SPC
Setup Menu appears on the display with existing setup
records. Otherwise, the Add option is highlighted.
Note also that the setup menu contains three setup records,
and that the first setup record, “Width Measurements,” is
highlighted. All three of these setup records were prepared
earlier by someone using either the short or long SPC setup
menu.
At this point, you can highlight an existing setup record and
perform SPC operations.
Note: The setup record that you select must correspond to
the configuration currently operating in the SLS. If you
need to change the SLS configuration, go to the
Conjguration Menu (described in Chapter S), highlight the
8-17