Installation guide

1.1 Customer Pre-Installation Checklist
Suggested site planning guidelines and tasks are listed
below. The tasks can be completed before system delivery.
To facilitate the installation process, it is recommended that
the customer plan ahead and coordinate site planning and
scheduling details with Digital.
Planning the Site
Plan the physical layout of the system cabinet, disk or tape cabinet,
console terminal, and other system units.
Plan to place all equipment away from heavy traffic centers.
Determine number, type, and location of required AC power receptacles
and circuit breakers.
Determine system power consumption to calculate the input line power
requirements.
Obtain cabinet weights and dimensions to check against floor loading
restrictions.
Determine environmental cooling requirements.
Checking the Delivery Route
Check the height, width, and location of doors and passageways.
Check floor loading requirements and protective covering along
passageways.
If applicable, check the size, capacity, and availability of the elevator.
1–2 VAX 6000 Series Installation Guide