6. Install the wire rope from the winch to sheave (8) in the upper sheave block. Install the wire rope over sheave (8)
from the front of the machine toward the rear of the machine.
7. Install the wire rope under sheave (9) in the lower sheave block.
8. Install the wire rope over sheave (10) in the upper sheave block.
Figure 34: Inserting wire rope into cable anchor
9. Insert the wire rope into the pocket and around the wedge (11). Allow an additional length of cable to form a tail
end (six inch minimum). Use a mallet to tap the wedge and the wire rope into the pocket.
10. Insert the tail end of the wire rope through clamp (12). Add a short piece of wire rope through clamp (12) in order
to secure the clamp, as needed. Tighten the nuts on the clamp.
Note: Do not clamp the loaded end of the wire rope and the tail end of the wire rope together.
11. Apply the first load in order to seat wedge (11).
Boom Pivot Pins – Lubricate
The grease fittings for lubricating the boom pivot pins are located on the left side of the machine.
There is one grease fitting for each pin. The grease fittings are located on the end of the pin on the outside face of the boom.
Lubricate the boom pivot pins through the two fittings.
Figure 35: Boom pivot pins, grease fittings