Technical data
Commissioning
44 Installation and maintenance instructions ecoTEC plus 0020116700_06 
10
1
10.4  Filling the condensate siphon
 > Remove the lower part (1) of the condensate siphon by 
turning the bayonet fitting anti-clockwise.
 > Fill the lower section with water until about 10mm below 
the upper edge.
 > Re-attach the lower section to the condensate siphon.
10.11  Checking the gas setting
b
 Caution.
Risk of damage caused by a not permis-
sible setting.
Modifications to the gas pressure regulator 
on the gas valve can destroy the gas valve 
and cause operating faults on the boiler.
 > Never modify the factory setting for the 
gas pressure regulator of the gas valve.
1
10.5  Gas pressure regulator
Gas valves with gas pressure regulators (1) are not installed 
in all boilers. There are also versions without gas pressure 
regulators.
10.11.1 Factory setting
b
 Caution!
An incorrect gas group setting can cause 
operating faults or a reduction in the 
working life of the boiler.
If the boiler version does not correspond to 
the local gas group, there will be malfunc-
tions or you have to change components of 
the boiler ahead of schedule, e. g. do not 
use a LPG boiler on natural gas.
 > Before starting up the boiler compare 
the details of the gas group specified on 
the identification plate with the gas 
group supplied at the installation site.
If the boiler version corresponds to the local gas 
family:
 > Proceed as described below.
If the boiler version does not correspond to the 
local gas family:
 > Call Vaillant Service Solutions (0870 6060 777); Gas 
conversions must only be carried out by Vaillant Service 
Solutions.
 > You must not start up the boiler yourself.
i
  If a gas conversion to liquid gas has been carried 
out by Vaillant Service Solutions, the smallest 
possible partial load is higher than is shown in 
the display. The current values can be found in 
the technical data (¬section17).
The combustion of this boiler has been checked, adjusted 
and preset at the factory for operation on the gas group 
defined on the identification plate. No measurement of the 
combustion is necessary to set up the boiler.
Do not adjust the gas valve. 
 > Ensure 
 – that the boiler has been installed in accordance with 
these instructions,
 – the integrity of the flue system and the flue seals, as 
described in the ¬flue installation instructions 
enclosed with this boiler, and as described below,
 – a visual check is carried out on the boiler combustion 
circuit and the relevant seals,
 – that any defects have been corrected at this stage.
To further validate the integrity of the flue system and con-
firm correct operation of the boiler it is possible to conduct 