10 Commissioning 
At the time of commissioning, complete all relevant sec-
tions of the benchmark checklist found within the back 
pages of this document.
Ensure that the filling and purging programs P.06 and P.00 
have been allowed to run fully before the boiler is ignited 
for the first time.
a
 Danger!
Risk of poisoning and burns caused by 
escaping hot flue gas!
Hot flue gas can escape and cause poison-
ing and burns if the boiler is operated with 
an incompletely mounted or open air/flue 
gas duct or if the boiler is operated with 
internal leaks with the front casing open.
 > Operate the boiler
- for commissioning
- for testing purposes
- in continuous operation
only when the front casing is fitted and 
closed and the air/flue gas duct is com-
pletely mounted.
 > Exclusively for test purposes such as gas 
working pressure testing the boiler may 
be operated with the front casing 
removed for short durations ONLY but 
must have a completely mounted air/flue 
gas duct.
i
  The automatic air vent cap must be loosened 
before filling the heating circuit or recharging 
circuit and during operation.
Purge the heating circuit and the recharging cir-
cuit using the purging program P.00 
(¬section10.4).
Auxiliary service equipment:
The following test and measuring equipment is required for 
commissioning:
 –CO
2
 measuring instrument
 – Digital or U-tube manometer
10.1  Switching on the boiler
 > Press the on/off button (¬Operating instructions).
The basic display appears on the display.
10.2 Installation assistant 
The installation assistant is launched when switching on the 
boiler for the first time. It provides easy access to the most 
important test programs and configuration settings for 
installing the boiler. The installation assistant is displayed 
whenever the boiler is switched on until it has been suc-
cessfully completed.
You must confirm the start of the installation assistant. 
Once confirmed, all of the heating and hot water demands 
from the boiler are blocked. This status remains until the 
installation assistant is completed or cancelled.
If you do not confirm the start of the installation assistant, 
it will be closed 10 seconds after being switched on and the 
basic display will appear. The next time the boiler is 
switched on using the on/off button, the installation assist-
ant will be started again.
10.2.1 Language  
 > Select the required language using the minus or plus 
button.
 > Press the right selection button to confirm the selected 
language.
The language change must be confirmed a second time in 
order to avoid an unintentional change.
i
  If you unintentionally select a language that you 
cannot understand, you can change it again as 
described below.
 > Press the right selection button and the plus button 
simultaneously and hold them down.
 > Press the fault clearance key for a short time.
 > Keep the right selection button and the plus button 
pressed until the option for changing the language 
appears on the display.
 > Select the language of your choice using the minus key 
or the plus key. 
 > Confirm the change by pressing the right-hand selection 
button ("OK").
10.2.2 Filling mode
Filling mode (test program P.06) is activated automatically 
in the installation assistant for as long as it appears on the 
display. (¬section 10.4).
10.2.3 Purging
 > Start test program P.00 to purge the system 
(¬section10.4).
Unlike the way in which it is started in the test programs 
menu, the purge program P.00 is started in the installa-
tion assistant by pressing the minus button or the plus 
button.
In order to change the circuit that is being purged, you 