Technical data

Boiler Installation Sequence 5
Instructions for Installation and Servicing turboMAX plus and thermoCOMPACT R1 17
5.7 Gas supply (turboMAX plus)
•Connect the 15 mm compression gas service cock (1)
and 15 mm copper outlet tail (22mm copper tail with
837) (3) as supplied with the appliance (2) and tighten.
•Connect a gas supply pipe of not less than 15 mm
diameter to the copper tail (minimum 22 mm gas
supply pipe with 837).
•Tighten all connections.
(Ensure the gas supply pipework is adequately sized
such that a 20 mbar gas pressure is available at the
boiler inlet at full flow rate).
Fig. 5.6: Fitting the gas connection turboMAX plus
I
0
3
1
2
5.4 Install the flue system
Fit the flue restrictor to the boiler (if required) and
install the flue system (refer to separate air/flue duct
installation instructions for further information).
5.5 Fitting the boiler
Lift the boiler (3) up to the wall so that it is slightly
above the hanging bracket (1).
Note!
Lift the boiler from either side at the bottom
edge.
•Lower the boiler slowly onto the hanging bracket so
that the cross member at the rear of the boiler fully
engages onto the hanging bracket.
5.6 Removing boiler casing
•Turn both securing fasteners (1) anti-clockwise by 90°
to release control panel (2).
Pull the case (3) forward at the bottom to disengage
from the securing clips.
Lift the case slightly to clear the top locations and pull
forward to remove.
Fig. 5.5: Remove of boiler casing
VRC-VC
3
I
0
2
I
0
90°90°
1