Technical data

System ready
Operation
4-9
P/N 7135049A
E 2007 Nordson Corporation
VBC_Siemens
Initial Startup (contd.)
S Set service interval.
The service tasks that are to be indicated as well as the intervals
must be stipulated. For recommended intervals refer to section
Maintenance. The intervals may need to be adapted to the operating
conditions.
Refer to Overview / V16
S Additional parameters, depending on model of melter.
4. Set seven-day clock.
Refer to Overview / V8
5. Wait until the system is ready for operation.
Fig. 4-7
6. Tighten the gland bolt on the pump(s) (Refer to section Maintenance).
7. Enable the motor(s).
8. Switch on the motor(s).
Refer to Overview / M1 and V1 and Figure 4-28.